Biologists with the Stanley Park Ecology Society will be monitoring the treatment and control sites to observe for the regrowth and rooting of ivy and how the abiotic and biotic community engages with the works.

Observational Data Collected at Ivy Project Treatment and Control Sites

  • Number of structures present, both on the ground and hanging
  • Ivy growth and condition
  • Native plant growth (i.e., species, location, and abundance)
  • Litter or soil accumulation on structures
  • Wildlife use of structures

Date: August 19, 2009

Observations: Treatment Site

  • Three ground and five hanging nest structures present.
  • No English ivy or other plant growth observed on structures. Ivy dry.
  • Minor amounts of bigleaf maple and red alder leaf material accumulating on structures.
  • Minor use by tent spider(s) on lower portion of vertical ground structures (web material observed).
  • No other wildlife use observed.

Observations: Control Site

  • One ground structure present.
  • No English ivy growth observed on structure. Ivy dry.
  • Minor cone and leaf material accumulation on structure.
  • Minor grass and forb growth along edge of structure.
  • Minor use by tent spider(s) on lower portion of structure (web material observed). One harvest man spider observed along margin of structure.
  • No other wildlife use observed.

Date: September 16, 2009

Observations: Treatment Site

  • Three ground and five hanging nest structures present.
  • No English ivy or other plant growth observed on structures. Ivy dry, but not brittle.
  • Minor amounts of bigleaf maple and red alder leaf material accumulating on ground and hanging structures.
  • Two unknown spider species observed. One tent spider web present on ground and hanging structure. One sow bug on ground structure.
  • No other wildlife use observed.

Observations: Control Site

  • One ground structure present.
  • No English ivy growth observed on structure. Ivy dry.
  • Minor cone and leaf material accumulation on structure.
  • Minor grass and forb growth along edge of structure.
  • Minor use by tent spider(s) on lower portion of structure (web material observed).
  • No other wildlife use observed.

Date: October 21, 2009

Observations: Treatment Site

  • Three new ground and one hanging structure added on September 26, 2009. Total structures present: six ground and six hanging.
  • No English ivy or other plant growth observed on structures. Ivy dry, but not brittle.
  • Bigleaf maple leaf material and soil added to new ground structures, along with some moss. Minor amounts of natural bigleaf maple leaf material accumulating on structures.
  • One unknown orb web building spider species observed on hanging structure.
  • No other wildlife use observed.

Observations: Control Site

  • One ground structure present.
  • No English ivy growth observed on structure. Ivy dry.
  • Minor cone and leaf material accumulation on structure.
  • Minor grass and forb growth present along edge of structure.
  • Minor use of structure by tent spider(s) along the side and ground interface (web material observed).
  • No other wildlife use observed.

Date: December 2, 2009

Observations: Treatment Site

  • Total structures present: six ground and six hanging.
  • No English ivy or other plant growth observed on structures. Ivy dry, but not brittle. Limited decomposition.
  • Fungi present amongst leaf litter on ground structures. No other native plant species observed.
  • Abundant bigleaf maple leaf litter accumulated on structures.
  • No wildlife use observed.

Date: December 23, 2009

Observations: Control Site

  • One ground structure present.
  • No English ivy growth observed on structure. Ivy dry, but not brittle. Limited decomposition.
  • Abundant American beech leaf litter and minor Douglas fir cone and leaf litter accumulation on structure.
  • Minor grass and forb growth present along edge of structure.
  • No wildlife use observed.
Advertisements

2 responses to “Site Observations

  1. Greg Ferguson, Stewardship Coordinator

    The Ivy Project: Environmental Survey Information
    Date Observations Treatment Observations Control
    August 19, 2009 • Three ground and five hanging nest structures present.
    • No English ivy (Hedera helix) or other plant growth observed on structures. Ivy dry.
    • Minor amounts of bigleaf maple (Acer macrophyllum) and red alder (Alnus rubra) leaf material accumulating on structures.
    • Minor use by tent spider(s) on lower portion of vertical ground structures (web material observed).
    • No other wildlife use observed. • One ground structure present.
    • No English ivy or other plant growth observed on structures. Ivy dry.
    • Minor cone and leaf material accumulation on structure.
    • Minor grass and forb growth along edge of structure.
    • Minor use by tent spider(s) on lower portion of structure (web material observed). One harvest man spider observed along margin of structure.
    • No other wildlife use observed.

  2. Pingback: The Ivy Project | Sharon Kallis

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s